Real Estate: Exclusive Developer Interview with LCOR Executive Vice President Bill Hard

Share |
Jan 6 2012 - 10:27am

Can you tell us a little about yourself and your work at LCOR?

My 30th anniversary with LCOR will be in April 2012, we're a private real estate development company, and as for myself, I started off in real estate banking in the 1970s with Philadelphia National bank and I worked there for 8 years where I got a background in the real estate finance side and one of my customers was the one I am now employed by.  So I joined what was then known as Linpro in 1981, we changed the name and structure in 1992 and that’s when we became LCOR.  So were about to celebrate 20 years of being in business at LCOR.  So I joined in 1981 in the headquarters came down here in 1992 and have been working in development in this office since 1993, where I have run the office.  We are privately owned, we have a DC office (in North Bethesda) which I run and a NY office which a counterpart of mine runs up in NY and our corporate headquarters are between in Berwyn PA.  In our NY and DC office we generate the projects that the company does and the corporate office helps us out on the legal, finance, accounting, cash management, oversight of the company.  As a company we do primarily three legs of our stool.

Right now we are managing about 8000 multifamily housing units and about 7 million sq ft of commercial space between NY and DC.  Beyond that we provide asset management service primarily in multifamily housing for a little bit over 20,000 units nationally.

What are the differences in the company back then and today?

We are larger today than we were in 1992 and more focused geographically and when we formed LCOR in 1992 we had offices in a number of cities around the country, and in the mid 90s we realized it made a lot of sense to focus on our roots we started as a northeast regional based company and that’s kind of where we are today.  I think the biggest change we've gone through is taking on a number of big, very large complicated projects...In the D.C. area the Patent and Trademark headquarters, North Bethesda center, we own a couple hundred acres in Clarksburg that’s the former comstat campus, were involved in the rezoning of a large piece of property in Tyson’s corner that we expect to complete the middle of next year and hopefully be in the position to redevelop a 1960s apartment community into a high density type project, it’s one of the closest properties  to the [ future] Tysons East metro stop. 

We've done 7 high rise buildings in the DC area in the last ten years everywhere from Arlington County to the district to Fairfax and also Montgomery County.  We primarily focus on ground up development, we do have a fund with a major pension fund investor that does both development of multifamily and acquisition of multifamily.  We’ve done some acquisitions, in this region we've bought 3 existing projects four or five years ago and continue to manage those and reposition those as necessary.  The Tyson’s corner project will be a repositioning as well.  

How do you fund all your projects?

Typically we will look at a project and determining which fund or source of money makes sense.  For most of our multifamily residential developments has been done in recent years with this one fund we have with a major pension fund.  The Nuclear Regulatory Commission (NRC) building about a $130 million project with USAA out of San Antonio it kind of depends on the project who’s in the market whose not, were not locked into any one source of either equity or debt.  We use multiple construction lenders, permanent lenders, and equity partners so it’s varied of the years.  Most of them like to be private.  It s usually pension funds and insurance companies, we’ve had a couple deals capitalized with off shore money but that’s not recently it’s mostly pension funds and insurance companies. 

Can you elaborate the process of getting the funding for example with NRC?

For something like NRC, the context for NRC is important because of the time it happened, the government started looking for space for NRC in late 2008 early 2009, it was a very hard time to be in the market for capital because you had Lehman's bankruptcy in September of 08, the market crashed and it kind of shut down.  To its credit USAA stayed in the market when a lot of people had basically said we don't want to look at any new real estate right now, we either have problems in our own portfolio or our board of directors is saying let’s not talk about real estate right now because it’s not a good thing to be talking about.  So in the case of NRC, we as a company had control of the land, had developed the site plan and had done the plans to build a building.  So we invested that money early on in the project, when the General Services Administration issued a Solicitation for Offer (SFO). They wanted the people who responded to be able to identify their sources of capital because they were concerned that they would award the project to someone and they couldn't perform, and that had happened within their portfolio in 2008 because of problems in the marketplace so we teamed up very early with USAA we known them for years we'd never done a deal with them but we had talked about possibly doing deals they were in the market they were looking for this type of project which was a 100% government leased building with a long term lease in a good location and so we spoke with them over several months negotiated a transaction within that was subject to getting the lease awarded and signed by the government we were able to do that in October of 2009 so we formed our venture with them in the Fall of 2009 and finished getting our approvals from Montgomery County and working with the government on changes they wanted to see in the building and started construction in June 2010 and we'll deliver the building to the government in May/June 2012 and then probably have the building completed done by September.

Did you plan your timing to build this project or was it sort of a coincidence that they were looking and you had your plans ready and everything?

Well you can tell from the area that we are right across the street from the NRCs headquarters so when they issued their SFO they knew they wanted to be within a certain distance of the existing buildings because they have space from Rockville down to Bethesda and they wanted to get everyone back within easy walking distance and for meetings back and forth.  And so they drew a very small delineated area because they didn't want someone offering them a building in Gaithersburg or Germantown because that would kind of work against their goal of consolidating people and getting more efficient operationally.  So before the SFO was issued we had discussions with both NRC and GSA because we knew the need was going to be coming out and we told them what we could do and what our building had.  It was a great plan until 2008 came along things got much more difficult in the office market, fortunately for us they issued their requirements for space in late 08 so I think it was a combination of good planning on our part and their need coming ahead at the same time.  We were actually going to start the building on a speculative basis we thought we could get it financed, but the lean times in this business are pretty long measured typically in years not months and by the time we had gotten to the point to break ground the market had moved away from spec building and we were either going to get the GSA through NRC or private sector tenant or we weren’t going to build the building because it would have been too much risk.

Construction is going great were on schedule HOK is the architect, Turner is the General Contractor; both have done a very good job on the project.

Do you leave leasing to Transwestern or do you find your own tenants?

We primarily leave that to them, we don't have leasing in house at LCOR we bring in brokers use CBRE over in Virginia so that’s their primarily function.  However having said that, we are out all the time in the marketplace at industry functions  and we run into other brokers and certainly encourage them to call our friends at Transwestern if they have a client who might be interested in North Bethesda Client.

How do you evaluate properties in terms of doing a deal?

If you look at the type of real estate we've been involved in typically we do not like getting exposed on land.  So a lot of the work historically that we have developed, most of them are transit oriented.  We’re not going to go out into the green fields and buy a piece of ground and take it through entitlements.  We typically will either do what we did at North Bethesda Center which is we turned it into a joint development agreement with Ramada 11 years ago which gave us development rights.  We'll spend the money to get through approvals get entitlements go through site plans, planning legal environmental and all that but what we don’t like to do is pay x amount of dollars for a piece of land and then have to carry it for 2 or three years to get it through entitlements.  So mostly we structure our transactions that we take the ground down as the market permits and as we're ready to go and in exchange for the land owner not getting his money right away we're spending all the money it takes to get the property entitled.  So that has been our approach that’s how it worked on PTO, that’s how it worked here [North Bethesda Center].  Kind of every deal we have done has been pretty much that way.  Our NY office is the same approach, we just landed a very large renovation build to suit for the North American Headquarters of Novo Nordisk, which is a large drug company outside of Princeton New Jersey it’s about a 700,000 square foot deal and we worked very hard structuring the lease working with the people who owned the property who needed some development expertise and property management expertise which we brought to the table.  But until we had everything wrapped up and ready to go we didn't take the ground down, we didn't take the financing until everything was ready. 

You can't create a market, you create an environment but you can’t create a market you can’t make people come to you if people don’t want to rent apartments they’re not going to rent apartments in North Bethesda no matter how nicely they are built, the fact is North Bethesda is becoming a very attractive location for apartment renters and that’s where were about to start our second building but we wouldn’t do it if the market wasn't there. 

Do you think height limits hinders your project?

For our project there is no hindrance because our original zoning let us go to twenty stories throughout the site.  I don’t think it’s going to be a hindrance at all for us and I doubt it will be a hindrance at all for anyone else who is in the sector plan.  The planning concept is that most of the height is around the metro station and have it line the pike and fall away from the metro station as you move east to west.  I think that’s a good plan if you look at the Rosslyn -Ballston corridor that’s how that’s set up if you look at most major areas that’s pretty much how it works.  If you go down to Chevy Chase you have your height at the metro station you start falling away as you get closer to the neighborhoods with lower density retail. 

How are you working together with the other property owners in the White Flint Sector Plan area?

One of the guys in our office Mike Smith who is one of Principals, and is the guy in charge of North Bethesda Center has been at probably every meeting there has been with the county and adjacent property owners, its actually been a pretty cooperative process.  The private sector in general work with the county going through the master plan process talking about how do you pay for improvements, and we ended up with a three legged stool as to how local improvements road improvements, bridges, street scape are going to get paid for and that was all done through open and honest discussions.   So I think generally it’s been a very good example of how you should plan an area we had all the stakeholders involved, had disagreements, resolved them effectively and moving forward on the plan everybody agreed to.  We would not expect a lot of opposition in any sector as the plans move forward. 

Can you tell me more about your property in Clarksburg?

It’s a little over 200 acres, we have the existing building on the property it was Comstat, then Lockheed bought Comstat and Lockheed moved out.  We are working on a zoning plan that is a mixed use development combination of retail office, and both for sale housing and multifamily rental housing.  We would not do the for sale housing so we would look to sell off land to developers to do that.  We would expect to file that rezoning application sometime in first quarter of next year maybe second quarter. 

Now was the building itself designated historic?

It was talked about, it was brought to the planning board.  There was a proposal in front of the planning board seven years ago to designate it historic, we did not think it should be and the planning board agreed with us unanimously.  It’s not historic, having said that from discussions with the community we think we will preserve some elements of the building that are architecturally significant as part of the back and forth with the negotiations.  The architect was Cesar Pelli who's well known internationally.  The building is a special purpose building very difficult for us to see how to reuse it either residentially or commercially but we'll figure something out.  Most of the building will be torn down but a significant portion will probably remain. 

What’s the timeline on rezoning?

It’s probably 12 to 18 months, we are going to rezone according to the master plan, were not going to start from scratch.  If we file by Middle of next year we would expect to have it done second half of 2013 and then we would look to start the infrastructure development, and then sell off parcels to homebuilders and keep parcels that we would want to develop for ourselves primarily off the commercial and multifamily piece we would keep and develop for our own account. We are rezoning it to MXD.

Why are you involved in real estate what do you like it?

Well I’ll tell you a story that probably best explains why I like real estate.  Number one I am a liberal arts major, not an engineer but when we did the patent and trademark office development we did a partnering session and one of the people who facilitated the partnering session, we had about 100 people there, subcontractors architects, planners, we had legal people, the government, GSA and PTO. We were all asked to draw a stick figure of the role we saw ourselves playing and so I drew stick figures with puppets and at the top of that was the puppet master.

Because I don't know as much as anyone of these individual people but I still have to make decisions based on what they’re doing and give them guidance.  My kids are always asking me "why do you like going to work so much?"  I said because I always have a problem that I've never faced before and I have to figure out an answer to and I get to figure it out with very smart people who know more than I do about their subject matter.  And to me that’s the charge I get, it’s not the same.  The process of getting the buildings done is always different.  You are dealing with a wide range of people and wide variety of disciplines; environmental, legal, designs, architectural, planning, appraisals, lending, equity partners, and the developer gets to figure out how to make all those people come together with a project you can afford to build and that the market is going to accept.  It’s not brain surgery by any stretch of the imagination but it’s interesting and sometimes hard to do and you get to work with great people.  I sit with the contractors and every time I sit with a contractor I learn something new and different about how they view things about scheduling, estimating, critical path, all kinds of things.  They help guide me and hopefully I help guide them as well. 

What is the most difficult part of the process?

Probably the most difficult part is probably having to spend a significant amount of money early on in plans, legal, land use approvals before you know you have a project that makes sense financially.  You suspect you have a project that makes sense financially but you don't know because if it takes you 2 years to get from controlling a piece of property to a set of plans done and ready to go, the market could turn just like that.  You could be in a great market or a not so great market and in which case you have to make a decision to I go or don't I go and usually if it’s a bad market you’re not going to go and then you've got this money invested already.  I think the probably the hardest part of the job is trying to limit the amount of capital you’ve got invested in deals before you know you've got a project you can get financing for.  It’s one of the reasons why we buy land the way we do and control the land the way we do and one of the reasons why we focus on transit oriented development and either at or near metro stations.  With the transit sites it’s a little less abrupt with the ups and downs in the market.  The chances of getting a project successfully accepted by the market and capitalized with debt and equity are typically higher when you’re at an area with mass transit and there’s barriers to entry and you’ve had to go through a hard process to get ready to go.  The hardest part is trying to balance that risk reward thing and how much risk do you have before you can actually get going and get a reward out of it. 

What would you say is the overall cost of going through the planning department and paying fees and such?

It depends a lot on the project and what municipality you’re in.  If you want a range it’s probably anywhere between 1 and 3 million dollars we’ve got invested before we break ground on something.

A large piece of that 1 to 3 million is how much money have you spent on the actual building plans with the architect, that's a big part of it.  And the other biggest part is just in legal/land use, internal and overhead costs. 

Do you ever try transitional neighborhoods to do development?

We've looked at some of that, we were on one of the Prince George's County teams chasing the Health and Human Services Development, we were on the team for the New Carrollton metro station, and we would have liked to have gotten that one.  It’s hard to call New Carrollton transitional because there’s a lot there now but there’s a lot that still has to go there.  I would say by and large we haven’t, having said that we did do a building on Thomas Circle when it was just starting to transition.  We built an apartment building next to the National City Christian church; we actually leased the land from the church.  So we’ve done a little bit of that but I wouldn't say that we are "edge" developers.   

How is leasing in retail space different form office space different form getting tenants into apartment buildings?

The easiest thing is the residential, you build the building, the lease is governed by county lawso it’s not like you're negotiating your lease with your residential tenants.  We don’t do a lot of retail work, I’d say the complexities of a retail lease and a commercial lease are probably about the same so I don't think one is any easier than the other one.  When we were negotiating the lease for Harris Teeter,  that was no easier or more difficult than negotiating the lease for the Nuclear Regulatory Commission through the GSA. You've got the same type of business concerns about lease term and whose paying for the tenant improvements and whose responsible for operating expenses and what rent am I going to pay? What shape is the building going to be in and all those factors are the same whether it’s in commercial or retail tenant.

Has your company considered acquiring more office and retail with the downturn in the market and lower prices?

I don't think we’ve ever bought an office building and it’s not something were looking to do, our primary focused is on the development side.  If we're buying we're probably buying existing apartments, we're not looking at office at the current time.

What’s your best advice for someone that wants to be a developer?

I'd say it’s a great business. I think it’s a very interesting business but it requires a lot of patience.  If you’re expecting to come in and hit one or two or three deals a year, year in and year out you are probably not right for the business and you’ve got to be patient you’ve got to be detailed oriented.  And you've got to be able to work with a wide variety of personalities and talents most of whom are probably as smart if not smarter than you are.  Having said that the rewards are terrific, you can make good money but there’s tremendous psychological satisfaction knowing that you’ve pulled off something that not a lot of people can necessarily do.  And not because you’re smarter but maybe you worked a little bit harder and you were able to get a group of people together of different personalities to work together and find solutions.  It’s really a problem solving business and that to me is the satisfying part of the business.  There are a lot of people that are really interested in it and I think there are a lot of people good at it, but it’s not for everybody because it can be very frustrating.  It can be a long time between tying up a piece of property and putting a shovel in the ground.  For example, on the North Bethesda Center project we were awarded the property in 1997, we signed the agreement with Metro in January of 2001; we didn’t put a shovel in the ground until June of 2006. We had a growth moratorium in Montgomery County; we had to rezone it, the market crashed there for a little bit and all these things going on.  Fortunately we structured the transaction in a way that we could afford to wait and we invested the money to point in 2006 where we could start building.  People look at that and say wow that’s a great building and I would love to have done that.  I say it’s a great building and a financial success but its one of those overnight successes that took 5 and a half years.

Was there anything on that site or was it a greenfield?

It was a driving range and when we excavated the building we found a lot of golf balls.  There was a driving range and a little 9 hole mini golf course right there.  When we started working on the property some guys I know like to play golf and I told them whatever you do don't get a series of lessons there because at some point it’s going to close down.  Prior to that there was actually a house there going way back.  Metro acquired the property when they were building the red line, the entire 32 and a half acres.

Is there a developer or two that you admire?

I’ve gotten to know some of the senior guys at the different firms pretty well, Douglas Firstenberg from Stonebridge, the guys at JBG and the guys from Federal Realty Investment Trust and I think the DC area is fortunate to have some really high quality development companies.  Hines for example is international and what they are doing downtown at the City Center project is phenomenal with Archstone and (others).  There are a lot of developers around here that I admire that do a great job and hopefully we [LCOR] are mentioned in the same breath as they are.

Any other project outside of your own that you like a lot?

I like what’s happened in Bethesda, when I came here Bethesda was not the place to be.  I moved here in 1982 and there was a lot of old buildings spread out all over the place and there was no sense of here or there but it happened to have a Metro Station.  But [things have changed] Particularly with what Federal Realty Investment Trust has done over the years with Bethesda Row.  I think it’s a great example of the development community really doing something good over time.  There is something called Urban Plan where they go into the high schools an they’ll get a history teacher to commit a semester to a planning exercise and the kids get an RFP and they’re supposed to figure out how to re plan an area of a  town.  I sit on the city council and they have to make presentations to us at the end of the semester about why they're plan is best and why the economics works and the marketing.  I did it for BCC one year and I was talking to the kids afterwards and they said for the first time when I went over to Bethesda Row I actually looked up and started to think why does this place feel so good to me?  So the kids started thinking about the physical environment that got created.  What Federal has done and what JBG has done and some of the other developers on the residential side I think is terrific and hopefully something like that ultimately will happen up in North Bethesda where people can walk around and have a good sense of where they’re at and feel good being there.

I think a lot of that has to do with the strong architecture on Bethesda Row?

The county had a lot to do with that.  The county ran something called the "Beauty Contest" in Bethesda in the 1980s and they metered down development based on the quality of architecture and the quality of the commitment to the public environment, and public spaces.  They very carefully said we'll do X number of buildings a year and the best buildings will be the ones we approve.

They don’t do that anymore do they?

No, but in lieu of that in Bethesda is very strong streetscape guidelines.  The development community literally called it the "Beauty Contest "and helped set the framework for what Bethesda is today and Federal has built upon that with Bethesda Row.  If you talk to the Federal guys they’ll tell you Bethesda Row has been 17 years in the making, it was 9 phases for them, and so it didn't happen overnight.

What’s your favorite type of architecture?

I really liked what we did with PTO, its 2.5 million sq feet that doesn't feel like 2.5 million sq feet.  Skidmore Owings Merrill was the architect and everybody did just a really great job of taking a lot of square footage, working within the constraints of the design guidelines that Alexandria set up and did a great combination of traditional and modern.  The building I like the best in all of this area is probably the Newsuem, I think it’s phenomenal.  I probably tend a little bit towards modern but not over the top modern.

How much does the developer play in designing the building?

The developer has a lot to do with the design.  A lot of times it comes down to what can you afford to build, it’s one of the interesting tensions in the business.  It comes down to the architects wanting to do award winning architecture and the developer who doesn't want to pay for a set of plans that end up in the drawer somewhere because you can't get financing for it, so there’s a real tension there.  If we have to stretch a little bit on the cost side to put an element in the building that will make people comment upon or will like we will tend to do that.  NRC is a good example of that, the cheapest thing would have been to build a rectangle and don't do any curves or any notches or funny angles.  But with the NRC, HOK, also a world class architect, convinced us rightly so to curve the building along the Marinelli Street frontage to follow the road because the road curves slightly.  So our facade rather than being a straight line actually follows the curve of the road, the building follows the road and it’s all glass and looks pretty cool.  But it also wasn’t the cheapest solution so you typically end up with not the cheapest solution but something between what the architect wants and what the developer can afford.   

What percentage of the total cost of a building is the architectural design?

The actual cost of building is about 70% of the total project cost and then the balance is land, design, and finance costs. 

What types of things do you do to meet the LEED Silver rating?

It’s called Low E glass to cut down glare, we have very low parking ratios since we're right at [White Flint] metro which is a major plus.  All storm water is handled on site in probably the most advanced system the county has ever seen.  You get points for use of recycled materials, how you handle the construction waste, buying locally.  The concrete is local from Northern Virginia by Miller and Long; the glass came from Buffalo, NY which is in the 500 miles that is considered 'local'.  Its great glass and the same firm did the glass at PTO.  You get a lot of credit for underground parking and being on transit, those are kind of built in credits towards LEED silver.

As far as educational experience what do you think it’s important to study or know?

I got my liberal arts background and my Masters of International Relations from the University of Pennsylvania, but I didn't go to Wharton School of Business and never went to business school.  I always felt my liberal arts background, was a really good perspective in terms of dealing with multiple disciplines.  Having said that I envy the MBAs who are able to run the programs and spreadsheets much more quickly than I ever could.  I think some finance and numbers is very important whether its accounting or an MBA in finance or an undergrad degree in economics.  Some sense of numbers is going to determine whether or not you break ground.  Spreadsheets make everything look good but if the inputs aren’t good you have beautiful looking spreadsheets with all the wrong answers.  If you're too numbers oriented you might have difficulty dealing with all the people you work with in negotiations.  Most people in the office have a graduate degree of some kind whether in real estate or finance or accounting.  If you look at the undergrad degrees we have a couple engineers, an English major, international relations, history major, a civil engineering degree which is great particularly on the project management side because you understand on the ground level what is happening with the buildings.  So it’s sort of all over the place in terms of educational background but I do think some innate understanding of numbers really helps. 

Stocks, Trading and Investing